Getting a Demolition Permit in Albuquerque: The Realistic Order of Operations
June 2, 2026 | 6 min read
Most delays on Albuquerque teardowns do not come from the machine. They come from a form filed with the wrong office or a utility that was never shut off. This guide lays out the order that usually works, with the caveat that rules and forms change, so check current requirements with the City before you lock in dates.
First question: which jurisdiction?
Inside Albuquerque city limits, demolition permits go through the City of Albuquerque Planning Department's Building Safety division (ABQ-PLAN). Plenty of addresses with an Albuquerque mailing address, especially in the North Valley and the edges of the metro, sit in unincorporated Bernalillo County and are handled there. Rio Rancho is a separate city in Sandoval County with its own building department. Confirm the jurisdiction for your parcel before anything else.
The usual sequence
- Define the scope: Write down the address, building type, approximate age and whether this is a full teardown, a partial removal or an interior strip-out. Scope often determines which permit path applies.
- Check for historic or overlay review: Older buildings and parcels in or near historic districts or the Old Town overlay may need extra review first. See our article on pre-1945 buildings and the Landmarks Commission.
- Get the asbestos survey: A survey for asbestos-containing material is generally expected before demolition, and notification to the City's Air Quality Program may apply. See our asbestos and NESHAP guide.
- Schedule utility work and locates: Request NM 811 locates, and arrange disconnects for electric, gas, water and sewer through the providers, including the Albuquerque Bernalillo County Water Utility Authority where applicable.
- Apply for the permit: Your contractor or you submit the application with whatever supporting documents the City requires, which can include a site plan, contractor details and proof of disconnects.
- Schedule the work and inspections: Once the permit is issued, demolition is scheduled and the City may require inspections at certain points. Final site condition, such as filled excavations and removed debris, is often part of closeout.
Where the time actually goes
In our experience, the physical demolition of a house is usually the shortest step. Review queues, asbestos lab turnaround, the notification waiting period and utility disconnects tend to take longer. Starting those in parallel instead of in sequence is the single biggest schedule saver.
Questions to ask the City
- Is my parcel inside City limits or in Bernalillo County?
- Does the building's age or location trigger historic review?
- Is my project a demolition permit, an alteration permit or both?
- What proof of utility disconnects and asbestos work is required at submittal?
Albuquerque Demolition Co helps clients work through these steps and confirms the specifics for each address. Call (714) 333-0178 to talk through your project.